geosavvy
Geotechnical
- Aug 8, 2006
- 35
Currently our cities' Storm Water regulations dictate that the post-development peak flow rate must not exceed the pre-development peak flow rate. However, the regulations do not take into account the nature of the flow.
What I mean to say is that you can have a pre-development condition where runoff sheet flows accross a 500-ft property line, then take that entire flow post-development and discharge it through a single pipe onto the same property (as long as your overall peak flow rate is not increased).
Depending on the configuration of the property down stream, this change in flow sometimes causes flooding problems that did not ocurr prior to the development.
Another issue is when the subject property sheds runoff in multiple directions, but after development the basins are changed such that a particular adjacent property could getting more runoff than pre-development. In other words, an adjacent property that previouly 'caught' 30% of a sites runoff, could be getting 75% of the runoff after development simply based on restructuring the basins. As long as the overall peak flow rate of the site does not exceed pre-development conditions, this is ok to do (according to our storm water regulations).
I was curious if any of you deal with similar Storm Water management issues. Have any of you run accross regulations that pose more "creative" restrictions on how water is to be discharged onto adjacent property (othe than simply not exceeding the pre-developed conditions).
Thanks.
What I mean to say is that you can have a pre-development condition where runoff sheet flows accross a 500-ft property line, then take that entire flow post-development and discharge it through a single pipe onto the same property (as long as your overall peak flow rate is not increased).
Depending on the configuration of the property down stream, this change in flow sometimes causes flooding problems that did not ocurr prior to the development.
Another issue is when the subject property sheds runoff in multiple directions, but after development the basins are changed such that a particular adjacent property could getting more runoff than pre-development. In other words, an adjacent property that previouly 'caught' 30% of a sites runoff, could be getting 75% of the runoff after development simply based on restructuring the basins. As long as the overall peak flow rate of the site does not exceed pre-development conditions, this is ok to do (according to our storm water regulations).
I was curious if any of you deal with similar Storm Water management issues. Have any of you run accross regulations that pose more "creative" restrictions on how water is to be discharged onto adjacent property (othe than simply not exceeding the pre-developed conditions).
Thanks.