Drexl
Chemical
- Sep 10, 2009
- 115
Hi,
PED category for pipes (I-III, SEP) is selected based on medium, maximum allowable pressure and nominal size. Does there exist a consensus regarding where to draw the border between categories at branch-off pipes? For example a DN250 feedwater pipe with a DN50 branch off.
1. First possibility would be at the branch weld (the weld according to the bigger pipe, and the smaller pipe has its own category)
2. Second possibility would be at the first shut-off valve (category according to the DN250 pipe up to and including the valve)
3. Third possibility to categorize the whole connected pipe according to the bigger pipes category
The Guideline 2/28 (see link below, page 91) seem to suggest alternative 3, however i've seen examples of all three. Alternative 3 would in some cases lead to unreasonably high categories where two big systems are connected through a small pipes.
Drex
PED category for pipes (I-III, SEP) is selected based on medium, maximum allowable pressure and nominal size. Does there exist a consensus regarding where to draw the border between categories at branch-off pipes? For example a DN250 feedwater pipe with a DN50 branch off.
1. First possibility would be at the branch weld (the weld according to the bigger pipe, and the smaller pipe has its own category)
2. Second possibility would be at the first shut-off valve (category according to the DN250 pipe up to and including the valve)
3. Third possibility to categorize the whole connected pipe according to the bigger pipes category
The Guideline 2/28 (see link below, page 91) seem to suggest alternative 3, however i've seen examples of all three. Alternative 3 would in some cases lead to unreasonably high categories where two big systems are connected through a small pipes.
Drex