Penalty when Weld get repair

Status
Not open for further replies.

Aakashjha

Mechanical
Mar 18, 2012
15
IN
thread378-253192

Hello,

As per ASME B31.1 - Power Piping, Please tell me that is Penalty required when the joints fail ?
In our spec we have 10 % radiography.

Your prompt action will be highly appriciated.

Regards
Aakash
 
Replies continue below

Recommended for you

B31.1 requires either 100% radiography or none depending on temperature or temperature and pressure. It does not require 10% RT on pipe not subject to 100% RT. Asuming that the 10% RT requirement has been defined in other contract specifications, it is up the originator of the specification to define the need for progressive sampling as required under ASME B31.3. If progressive sampling is not defined, the rejected weld must be repaired and re-examined.
 