Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Permeability of lined tunnel

Status
Not open for further replies.

sango

Geotechnical
Oct 5, 2002
15
Dear all,

Any information on the permeability of segmental concrete lining that without gasket in the connections.

Thanks.
 
Replies continue below

Recommended for you

It seems like without gaskets, the joints would be more permeable than the concrete cross section?

Remember: The Chinese ideogram for “crisis” is comprised of the characters for “danger” and “opportunity.”
-Steve
 
It also depends on what type of joint is used (butt, knuckle, etc...). I have not had experience with an ungasketed tunnel lining that didn't have some sort of liner installed post-construction.
 
Dear lha,

You are right. The permeability of joint without gasket is much higher than the concretre section. Having such arrangement is to allow the liner behaving in "semi-drained" condition, in which water can be drained throught the joints.

In my case, dewatering is not a concern and the "rock" tunnel itself is stable even without lining, but the client would like to have lining. "Semi-drained" lining allows a more economic design than a "water-tighted" lining.

Any idea on estimating the permeability of the joints? so that water pressure on the semi-drained lining can be estimated.

Thanks!

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor