PFMEA VS 8D Report

Status
Not open for further replies.

SeasonLee

Mechanical
Sep 15, 2008
912
As I know, PFMEA is a widely used analysis procedure in the early stage of tooling development. Can we use PFMEA to analyze the problem for an approved part during production?

If there is any deviations noticed on an incoming part, we will issue a DR to reflect the discrepancies and request supplier to provide the corrective actions and preventive remedies in an 8D report. Are there any other ways to prevent the same problems happening again except through using the 8D report? Can we use PFMEA to analyze the problem at this moment?

Thanks for any inputs

Season
 
Replies continue below

Recommended for you

There are numerous ways (and acronyms) for dealing with parts and processing information.

I would not use a PFMEA alone to analyze a problem on an approved part during production unless the problem is one potentially caused by the processing itself. A design FMEA would be useful as well.

If you have deviations to a part and run it through your processes, expect to have different results and potential problems. Your processes cannot run "normally" when you intentionally introduce variation. Hopefully you know the risks and costs beforehand to help make the choice on whether or not to use a discrepant component.

A PFMEA is not likely to be of help for immediate problems other than to illustrate and capture potential causes. You would still need to look for the actual one(s). Hopefully there are additional quality metrics in place that provide current data on how the processes are performing.

Regards,
 
Sounds like you're trying to do your supplier's job for him, yet, you're asking him to generate an 8D report, wherein, disciplines 5,6, and 7 relate to the correction of the problem. If the problem persists, then, either the supplier's 8D was wrong, or he's not implementing his corrective actions.

In either case, what would any analsis done by you have any bearing on the problem at hand?

TTFN