GeotechD
Geotechnical
- Jul 5, 2005
- 5
We performed two static pile load tests on AGPD piles of 16 and 18 inches diameter and 75 feet long. the cage length was 40 feet and the central rebar continued to the pile tip. the subsoil conditions was typical in central Florida (Loose sands followed by silty/clayey sands and sandy clays then the limestone). these piles did not reach the limestone and they are basically friction piles. There was a fat mediun to stiff clay layer at depth 40 to 50 feet.
The 16-inch pile was able to sustain a load of 300 tons and was settled only 0.6 inch. The 18-inch pile failed to carry the same load and excessive settlement began at 240 tons even without increasing the load on the pile.
I have some thoughts and I need your comment and suggestions:
1- There is nicking at or close to tip of the cage that may be occured due to the developed positive pore water pressure through the fat clay layer under the existing overburden pressure (it is a contractive soil). The method of installation of this type of piles may cause excess lateral stresses in the undrained conditions (beccause it is fast)and if the soil is contractive, positive pore water pressure will develop and the time of installation is not enough for it to dissipate, so it may cause nicking to the fresh concrete.
2- There was a .07 inches difference between the two used dial gages, which implies that there was some type of excentricity. May be the pile is structurely damaged at the tip of the cage due to excessive bending moment resulted from the excentricity. There are some evidences supporting that assumption; the recation piles on one side were pullet up a little bit. The dial on that same side has more settlement that the other gage.
Any comments or ideas will be greatly appreciated.
The 16-inch pile was able to sustain a load of 300 tons and was settled only 0.6 inch. The 18-inch pile failed to carry the same load and excessive settlement began at 240 tons even without increasing the load on the pile.
I have some thoughts and I need your comment and suggestions:
1- There is nicking at or close to tip of the cage that may be occured due to the developed positive pore water pressure through the fat clay layer under the existing overburden pressure (it is a contractive soil). The method of installation of this type of piles may cause excess lateral stresses in the undrained conditions (beccause it is fast)and if the soil is contractive, positive pore water pressure will develop and the time of installation is not enough for it to dissipate, so it may cause nicking to the fresh concrete.
2- There was a .07 inches difference between the two used dial gages, which implies that there was some type of excentricity. May be the pile is structurely damaged at the tip of the cage due to excessive bending moment resulted from the excentricity. There are some evidences supporting that assumption; the recation piles on one side were pullet up a little bit. The dial on that same side has more settlement that the other gage.
Any comments or ideas will be greatly appreciated.