I was just curious
You have a long pile that goes all the way down through very weak layers of soil only to touch the first firm layer available, usually rock.
And for some reason no penetration is made into rock.
So you have bearing capacity. Fine.
But even if piles are connected to each other at the top, by a very rigid cap, will you have lateral resistance in the piles.
Nice summer holidays pals
IJR
You have a long pile that goes all the way down through very weak layers of soil only to touch the first firm layer available, usually rock.
And for some reason no penetration is made into rock.
So you have bearing capacity. Fine.
But even if piles are connected to each other at the top, by a very rigid cap, will you have lateral resistance in the piles.
Nice summer holidays pals