Hi,
Attached is a foundation plan for grade beam which is supported by piles. You will see the the column load ( Pmax) lines with center of one the piles at Section A. I am trying to take the advantage of 3 ft thick grade beam and use springs for pile supports. Instead of applying 100 % of the Pmax to one pile, Has anyone an opinion or a reference that explains What percentage of Pmax can be distributed to the other pile which is 3.5 ft apart?
Thank you
Attached is a foundation plan for grade beam which is supported by piles. You will see the the column load ( Pmax) lines with center of one the piles at Section A. I am trying to take the advantage of 3 ft thick grade beam and use springs for pile supports. Instead of applying 100 % of the Pmax to one pile, Has anyone an opinion or a reference that explains What percentage of Pmax can be distributed to the other pile which is 3.5 ft apart?
Thank you