Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Piling Tolerances

Status
Not open for further replies.

ataman

Structural
Dec 7, 2006
53
0
0
PA
Hi,

Would just like to get some feedback on the plumbness tolerances that are generally accepted for driven piles.

Thanks.
 
Replies continue below

Recommended for you

I typically use 2% max variation from plumb.

This is subject to modification. Piles in groups can deviate quite a bit more, as long as the piles are not interfering with each other and the pile cap can perform properly.

Oftentimes the real issue is the eccentricity of reaction. If a pile is not plumb, it must be determined what is out, either the toe or the head. Is the pile a single or part of a group? The issue usually becomes a problem of statics.
 
I have always found plumbnss tolerances interesting.

a.) How do you check plumbness of say a 60 ft pile driven into the ground?
b.) what if the pile is plumb at the top and sweeps?
c.) How are the tolerancecs decided? Do they reflect the design capacity vs. design load?
d.) what happens if the pile is found out of plumb? How do you corrrect it and who pays?

Note that as innocent as these questions seem, they have sparked heated debates and firece arbtrations for a very long time.

Any thoughts?
 
Piles that are encased in a pile cap are very forgivng. The nominal +/- 3" can easily be extended to 15" for interior piles. The usual FS from the geotech giving net usable from ultimate is of an order of 3, thus a minor deviation from plumb will shrink the FS by the cosine of the deviation from vertical. Usually not even significant up to 10 degrees of lean, (2 inches in a foot). My specs have no deduction for out of plumb piles and require additional piles only for attempts that fail to achieve design depth.
 
Status
Not open for further replies.
Back
Top