shersan
Electrical
- Jun 17, 2002
- 11
Dear All ,
Please enlighten me with some good solutions .
In our 11kV electrical distribution systems ,Five nos of 11kV substations(connected as Ring ) are fed from 2nos, 800 A feeders of 33/11kV primary substation . The ring in & ring out cables are 2 Runs of 3cx 185 sq mm PILC/Al cables and all switchgears are almost 20years old . Ring in Ring out feeders on 11kV substation are protected with only pilot wire protection with translay relays .Now the utility decided to change the incoming cable with 1 x 240 Sq mm XLPE/Cu cables inplace of 2 Nosof 3cx 185 sq mmm PILC and we might need to change the protection relay with normal MICOM P121 realy ( E/F & O/C)in place of translay relay on our 11kV S/S due to the source (utility ) substation feeders are protected with VA Tech DCD O/C & E/F relays .
As the 33/11kV ,2 feeders are sharing the whole connected load on our 5 nos 11kV S/S , what kind of protection realay at the incoming point of these 5 S/S ' s is advisable ???? The ring is connected in the following sequence . 33/11kV ( feeder 1 )ring in to S/S -to S/S 2 to S/S 3 to S/S 4 to S/S 5 to 33/11kV ( feeder 2 ) .Mostly all connected loads crane loads .Supply continuity is paramount in the event of fault in any of the 5 S/S's .
Please enlighten me with some good solutions .
In our 11kV electrical distribution systems ,Five nos of 11kV substations(connected as Ring ) are fed from 2nos, 800 A feeders of 33/11kV primary substation . The ring in & ring out cables are 2 Runs of 3cx 185 sq mm PILC/Al cables and all switchgears are almost 20years old . Ring in Ring out feeders on 11kV substation are protected with only pilot wire protection with translay relays .Now the utility decided to change the incoming cable with 1 x 240 Sq mm XLPE/Cu cables inplace of 2 Nosof 3cx 185 sq mmm PILC and we might need to change the protection relay with normal MICOM P121 realy ( E/F & O/C)in place of translay relay on our 11kV S/S due to the source (utility ) substation feeders are protected with VA Tech DCD O/C & E/F relays .
As the 33/11kV ,2 feeders are sharing the whole connected load on our 5 nos 11kV S/S , what kind of protection realay at the incoming point of these 5 S/S ' s is advisable ???? The ring is connected in the following sequence . 33/11kV ( feeder 1 )ring in to S/S -to S/S 2 to S/S 3 to S/S 4 to S/S 5 to 33/11kV ( feeder 2 ) .Mostly all connected loads crane loads .Supply continuity is paramount in the event of fault in any of the 5 S/S's .