JoelTXCive
Civil/Environmental
- Jul 24, 2016
- 927
I do not have a lot of experience with pipe piles, but we have a project where the soil conditions were so poor that my normal go-to of drilled shafts will not work.
The geotech has recommended 18" x .375" wall thickness driven piles.
These are dry-land piles in a fresh water environment. For corrosion protection, I specified a fusion bonded epoxy for the top 8ft of the piles.
The contractor has submitted an RFI to use 16mil coal tar epoxy for the entire pile length (~50ft).
I have a conference call on Monday to discuss with the contractor.
Any questions I should ask? Is the soil-to-pile friction coefficient different?
Thank you in advance.
The geotech has recommended 18" x .375" wall thickness driven piles.
These are dry-land piles in a fresh water environment. For corrosion protection, I specified a fusion bonded epoxy for the top 8ft of the piles.
The contractor has submitted an RFI to use 16mil coal tar epoxy for the entire pile length (~50ft).
I have a conference call on Monday to discuss with the contractor.
Any questions I should ask? Is the soil-to-pile friction coefficient different?
Thank you in advance.