zengx
Mechanical
- Apr 8, 2012
- 27
For a 230 km 26" CS pipeline that has been hydrotested (by sections), we need to perform the final lay-up.
After the pipeline sections have been hydrotested separately with the valves being not installed; the golden joints for the valves and the hydrotest limits have been completed.
The drying of each tested section, after disposing the water, was achieved by performing several runs of foam pigs.
The question is: Now, we already completed the whole pipeline, do we need a final complete run of additional pig(s) before the lay-up ?
Note: Lay-up will be done by dry air.
Mohammed Diab.
Inspection Supervisor - Saudi Aramco.
After the pipeline sections have been hydrotested separately with the valves being not installed; the golden joints for the valves and the hydrotest limits have been completed.
The drying of each tested section, after disposing the water, was achieved by performing several runs of foam pigs.
The question is: Now, we already completed the whole pipeline, do we need a final complete run of additional pig(s) before the lay-up ?
Note: Lay-up will be done by dry air.
Mohammed Diab.
Inspection Supervisor - Saudi Aramco.