I am trying to make a report from MS Project without using excel that will give me planned vs. actual work for every resource by summing up their charges from individual work packages.

I am not able to create a report that will look somewhat like this....Can someone help?

Resource Name WeekEnding Planned Work Actual Work
------------- ---------- ------------ -----------

For past weeks the Work field will become equal to actual work and if the resource is not baselined with the workpackage I won't have the baselinework, so, what field I should be looking at?

Please help me out in this....

Thanks a bunch..

Rex
 