Planning Units

Status
Not open for further replies.

nyclow2

Civil/Environmental
Sep 3, 2006
2
I managed to copy the schedule from one project to another. However, it did not solve my problem.

While in the copy window generated from tools, project utilities, under "To" i changed the planning units to days from hours on the from/ original. However everything is still displayed in hours on the copied schedule.

For exmaple the Total float and the Original & Remaining Durations are all still in hours.

Originally the schedule was generated in Suretrak 3.0A. Since i converted it into P3 everything is in hours.

If anyone has a solution to the above, i would be extremely grateful.
 
Replies continue below

Recommended for you

In P3 you can assign each activity a seperate calendar. You can have several calendars for many different senarios like shift work etc.

It appears that during the conversion all of your activities were assigned to a calendar that is in hours. You will need to either change that calendar to days or make a new calendar in days and assign each activity to that calendar.
 