daaguirre
Mechanical
- Jun 2, 2016
- 19
Hi Everyone,
I recently graduated from college (Mechanical Engineering) and started working as a Plumbing engineer at a small company. I am currently the only plumbing engineer at my office and I would like to hear your suggestions about how to present the different plumbing systems in the floor plan drawings. For example, for the building and plumbing systems shown in the attached figure, I've seen two ways of preparing the drawings, are both of them correct, and if so which one is more common ? (in the United States).
Option 1
Roof Plumbing Plan: Shows the storm drainage below the roof (level 4)
Level 3 - Plumbing Plan - Domestic Water: Shows the domestic water system (Above level 3)
Level 3 - Plumbing Plan - Drainage: shows the sanitary drainage system below level 3 (that one corresponding to the fixtures on level 3)
Level 2 - Plumbing Plan - Domestic Water: Shows the domestic water system (Above level 2)
Level 2 - Plumbing Plan - Drainage: shows the sanitary drainage system below level 2 (that one corresponding to the fixtures on level 2)
Level 1 - Plumbing Plan - Domestic Water: Shows the domestic water system (Above level 1)
Underground Plumbing Plan: the sanitary drainage system below level 1 (that one corresponding to the fixtures on level 1)
Option 2
Roof Plumbing Plan: Shows only the roof drains
Level 3 - Plumbing Plan - Domestic Water: Shows the domestic water system (above level 3)
Level 3 - Plumbing Plan - Drainage: shows the storm drainage (above level 3)
Level 2 - Plumbing Plan - Domestic Water Shows the domestic water system (above level 2)
Level 2 - Plumbing Plan - Drainage: shows the drainage system above level 2 (that one corresponding to the p. fixtures on level 3)
Level 1 - Plumbing Plan - Domestic Water Shows the domestic water system (above level 1)
Level 1 - Plumbing Plan - Drainage: shows the drainage system above level 1 (that one corresponding to the p. fixtures on level 2)
Underground Plumbing Plan: shows the drainage system below level 1 (that one corresponding to the plumbing fixtures on level 1)
For reference, in the figure, blue is domestic water, purple is storm drainage and green is sanitary drainage.
With regards to the vent system, we typically show it on the same drawings as the domestic water. I've seen people present it on the same drawings as the sanitary system using a dashed line pattern. However, because of the way we prepare the drawings in Revit, it seems easier to show it on the domestic water drawings.
Thanks in advance for your help!!.
Also, If you have any reference material that you would like to suggest me, feel free to mention it. (I am currently using the International Plumbing Code and the ASPE Plumbing Engineer Design Handbook).
I recently graduated from college (Mechanical Engineering) and started working as a Plumbing engineer at a small company. I am currently the only plumbing engineer at my office and I would like to hear your suggestions about how to present the different plumbing systems in the floor plan drawings. For example, for the building and plumbing systems shown in the attached figure, I've seen two ways of preparing the drawings, are both of them correct, and if so which one is more common ? (in the United States).
Option 1
Roof Plumbing Plan: Shows the storm drainage below the roof (level 4)
Level 3 - Plumbing Plan - Domestic Water: Shows the domestic water system (Above level 3)
Level 3 - Plumbing Plan - Drainage: shows the sanitary drainage system below level 3 (that one corresponding to the fixtures on level 3)
Level 2 - Plumbing Plan - Domestic Water: Shows the domestic water system (Above level 2)
Level 2 - Plumbing Plan - Drainage: shows the sanitary drainage system below level 2 (that one corresponding to the fixtures on level 2)
Level 1 - Plumbing Plan - Domestic Water: Shows the domestic water system (Above level 1)
Underground Plumbing Plan: the sanitary drainage system below level 1 (that one corresponding to the fixtures on level 1)
Option 2
Roof Plumbing Plan: Shows only the roof drains
Level 3 - Plumbing Plan - Domestic Water: Shows the domestic water system (above level 3)
Level 3 - Plumbing Plan - Drainage: shows the storm drainage (above level 3)
Level 2 - Plumbing Plan - Domestic Water Shows the domestic water system (above level 2)
Level 2 - Plumbing Plan - Drainage: shows the drainage system above level 2 (that one corresponding to the p. fixtures on level 3)
Level 1 - Plumbing Plan - Domestic Water Shows the domestic water system (above level 1)
Level 1 - Plumbing Plan - Drainage: shows the drainage system above level 1 (that one corresponding to the p. fixtures on level 2)
Underground Plumbing Plan: shows the drainage system below level 1 (that one corresponding to the plumbing fixtures on level 1)
For reference, in the figure, blue is domestic water, purple is storm drainage and green is sanitary drainage.
With regards to the vent system, we typically show it on the same drawings as the domestic water. I've seen people present it on the same drawings as the sanitary system using a dashed line pattern. However, because of the way we prepare the drawings in Revit, it seems easier to show it on the domestic water drawings.
Thanks in advance for your help!!.
Also, If you have any reference material that you would like to suggest me, feel free to mention it. (I am currently using the International Plumbing Code and the ASPE Plumbing Engineer Design Handbook).