OxEng
Civil/Environmental
- May 31, 2018
- 1
I am reviewing a design of an underground detention system that is using 96-inch diameter storage pipe. The design engineer is modeling the control for the pond node as an 18-inch diameter culvert for the primary outlet and routing a weir plate with orifices through it. However, the plan layout has the control structure shown as a 2-foot diameter manhole located downstream of the storage pipe with 45 feet of 18-diameter pipe connecting them.
It still appropriate to model it this way or should the actual outlet from the pond node be an 18-inch diameter culvert that then connects to a catch basin node representing the control?
It still appropriate to model it this way or should the actual outlet from the pond node be an 18-inch diameter culvert that then connects to a catch basin node representing the control?