I'm currently working on a project with an area of 38 acres. The requirements are to reduce the discharge resulting from the 25, 50, and 100 year 24 hour storms by 25% after development. That's not my problem, just a little background.
The site is situated in a wetlands area. The local agencies recommend using the heavily wooded condition for predevelopment rates, which is fine. The developer would like the detention pond to be an 8 acre wet pond. What CN value should I use to model this pond post-development? Should I assume that all rainfall that falls over this 8 acres will runoff? The DOTD manual I am referencing does not provide any values for this condition.
The site is situated in a wetlands area. The local agencies recommend using the heavily wooded condition for predevelopment rates, which is fine. The developer would like the detention pond to be an 8 acre wet pond. What CN value should I use to model this pond post-development? Should I assume that all rainfall that falls over this 8 acres will runoff? The DOTD manual I am referencing does not provide any values for this condition.