Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Post Crash Advice - progress updates

Status
Not open for further replies.

TheBIgManc

Specifier/Regulator
May 13, 2004
1
0
0
GB
Morning,

Today I have recovered 11 plans from backup tape of my 27 that have crashed due to a 'Resource Pool' error.

All 11 are now exibiting unusual effects when updated via progress mail (e-mail updates). I have no effort driven tasks though some if not most were before the crash.

When the time is updated for a particular day, all is fine. When the next day is updated, the previous day is made zero and the current day shows the right hours. This follows for all subsequent days that are updated...does this description make sense to you!?!

This is now having catastrophic effects in my reports.

Many thanks in advance.

 
Status
Not open for further replies.
Back
Top