Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Post-tension 7 wire strand at turning point

Status
Not open for further replies.

Spritediet

Structural
Jul 18, 2024
1
0
0
CA
So I've been working on these 1940-1950 heavy timber trusses for a couple of months to plan for some repair.
We now are at the construction phase of the project and the GC recently asked if he could remove the teflon (or PEHD?) pads from under the post tensioning cables at the turning points:
02_vnc91h.jpg
01_kjgck4.jpg


It seems obvious to me that these pads have an important influance on the load distribution a the interface between the cables and the supports. The issue is the GC says these pads allow the cables to slip sideways while retensionning the cables, whitch presents a safety hazard.

I was wondering what was the outcome of this older thread (thread507-456196) or if anyone might have an opinion on the matter.

Thanks guys!
 
Replies continue below

Recommended for you

OP said:
It seems obvious to me that these pads have an important influance on the load distribution a the interface between the cables and the supports.

Agreed. If the cables don't slip along the length of the beam, you'll develop a bunch of unintended stresses in the deviators.

OP said:
The issue is the GC says these pads allow the cables to slip sideways while retensionning the cables, which presents a safety hazard.

I feel as though I'm seeing guard / lip elements at the sides of the deviators that would address such a concern.
 
Status
Not open for further replies.
Back
Top