jguer005
Structural
- Apr 11, 2014
- 10
Doing some research into Post-Tensioning for a project coming up, and most of the resources I have read state that a "target range" for balancing loads in a PT slab is 60-80% of the DL.
Is this arbitrary, or is there some minimum requirement that I am missing?
Is this arbitrary, or is there some minimum requirement that I am missing?