queen
Electrical
- Feb 25, 2002
- 1
Using 16" sch 120 Carbon Steel pipe, to effect two tie in points (welded) what PWHT and Test would be required BY B31.3 The existing line cannot be hydrotested as it would take about 3 weeks to fill and drain etc?
REGARDS
queen
REGARDS
queen