cnstengineer
Civil/Environmental
- Nov 26, 2011
- 15
I'm working on a project where we are installing concrete piers that are drilled approx 24 - 25' below grade. The drilled caisson portion of the pier has a signficant amount of water in the hole. The contractor would like to pour the piers using the tremie method and pump the water from the top of the hole as the concrete is poured, displacing the water from the bottom up. Is it okay to leave the concrete un-vibrated? I'm concerned with vibrating the concrete and mixing the water in with the concrete. Also, how should the top portion of the concrete be handled, as this will most likely be contaminated with the water? Should this be chipped away to get down to sound concrete?