goldilocks
Computer
- Oct 5, 2001
- 5
I'm about to take my first stab at pouring a footer about 2-1/2 ft below the water table. And as always, I don't really know what I'm doing. Can anybody offer helpful advice?
1) I understand that concrete will harden under water, but does that reduce its strength? would it help to line the trench with plastic sheeting? Or is that not necessary?
2) Does a footer need to be wider under water than if it were in dry ground (because the soil is not as compacted, I assume)?
3) Is it common practice to bring such a footer up above the water table before building on it (I will be putting a 10' high poured wall on it)? That would make it easier to do the wall, but I would have a REAL thick footer.
Thanks for any help--
-G
1) I understand that concrete will harden under water, but does that reduce its strength? would it help to line the trench with plastic sheeting? Or is that not necessary?
2) Does a footer need to be wider under water than if it were in dry ground (because the soil is not as compacted, I assume)?
3) Is it common practice to bring such a footer up above the water table before building on it (I will be putting a 10' high poured wall on it)? That would make it easier to do the wall, but I would have a REAL thick footer.
Thanks for any help--
-G