Plinko
Electrical
- Oct 29, 2001
- 12
When intalling a new power transformer, it seems every engineers rule of thumb is to let it 'soak' for a day or two before loading the bank. I understand why it is a good idea to practice this rule (i.e. sudden change in temp., windings may have been damaged during the move, oil dispacement, etc.), but I don't know if it's always necessary.
I have a situations where I need to remove an older tfr and replace it with a new 10/12.5 MVA tfr. The 10MVA tfr will be moved about two miles on the day of the swap. I would like to energize and load it the same day. The initial load will be about 2-3 MW & be loaded to about 6 MW withing 24 hrs.
My question (finally!!)...Am I at risk if I soak the 10MVA tfr for a few days to get the oil and winding temp to a no load temp....move the tfr to it's new location....energize and load it on the same day? I know it shouldn't be done bu can it be done? And why?
Thanks in advance and sorry for the long question.
I have a situations where I need to remove an older tfr and replace it with a new 10/12.5 MVA tfr. The 10MVA tfr will be moved about two miles on the day of the swap. I would like to energize and load it the same day. The initial load will be about 2-3 MW & be loaded to about 6 MW withing 24 hrs.
My question (finally!!)...Am I at risk if I soak the 10MVA tfr for a few days to get the oil and winding temp to a no load temp....move the tfr to it's new location....energize and load it on the same day? I know it shouldn't be done bu can it be done? And why?
Thanks in advance and sorry for the long question.