trouthunter
Electrical
- Nov 5, 2001
- 1
We are a nuclear power generating station, and will be replacing a reserve station service transformer with an auto load tap changing transformer (make and model yet to be determined). We are currently in the conceptual design stage. The old transformer (oil filled) is 115kV/4.16kV, 12.5 MVA, Y-Delta-Y. The new transformer (oil filled) will be 115kV/4.16kV, approx. 18 MVA, Y-Delta-Y. the cooling arrangement has not yet been decided. There will be limited time available for the installation and testing, including removal of the old transformer (about 20 days). Has anyone performed this type of transformer installation? If so, what type of factory and field testing did you specify (what standards)? Do you have any lessons-learned to share? The installation and testing may be performed during March/April time frame, so the weather could include freezing temperatures and/or snow.