Charlie.A
Electrical
- Jan 31, 2020
- 1
Was wondering what best practices are used when considering a stored power transformers that has never been in service and is approximately 17 years old. An example of type of transformer would be that of a 40MVA, sealed unit with fins installed, filled with oil with a N2 blanket. Looking for info. on recommended testing intervals and necessary tests to perform on STORED never in service unit. Thank you.
Charlie.A
Charlie.A