Good day:
We are pre-assembling a roof of a structure, which will be raised 20 meters high, the client requests a topographic protocol, it demands tolerances of the final structure for this pre-assembly at ground level.
The ceiling has the dimensions 10 x 20 meters.
That is good?

THANKS