PRE ENGINEERD BUILDINGS Tonnage Cost $ .

Status
Not open for further replies.

malikasal

Structural
Joined
Nov 17, 2013
Messages
130
Location
AE
Hi

If we are talking about the US market, how much do the PEB fabricators approximately sell the MTON to the customer? including ( fabrication and finishing).





ôIf you don't build your dream someone will hire you to help build theirs.ö

Tony A. Gaskins Jr.
 
Their costs are very similar to any other fabricated steel. Their economy is:
[ol 1]
[li]Having a one stop shop (engineering, architecture and detailing).[/li]
[li]Optimizing the design. Much of their design effort is to use light sections such as plate fabricated tapered columns and beams; cold formed Z purlins, etc. [/li]
[/ol]
 