Working on my first parking garage. It is a hybrid structure of precast columns, beams, double T slabs and cast in place shear walls. Lateral loads to be transfered to shear walls by floors acting as rigid diaphragms. 3" cast-in-place topping will be provided.
Questions:
1-What are considered to be the diaphragm chords? The L-beams or some type of additional reinforcing?
2- Who designs these chords; the precast engineer or the engineer of record of the building?
3- Who designs the connections between different precast elements to resist lateral loads?
Thanks for the help
Questions:
1-What are considered to be the diaphragm chords? The L-beams or some type of additional reinforcing?
2- Who designs these chords; the precast engineer or the engineer of record of the building?
3- Who designs the connections between different precast elements to resist lateral loads?
Thanks for the help