tw
Structural
- May 30, 2001
- 70
We recently had a problem whereby some precast spandrel panels were erected by attaching to the steel floor beams prior to the concrete floor slab being poured. The floor beams are all design as composite steel beams. In one particularly heavy panel, the weight caused excessive deflection in the supporting steel and erection was halted. After looking at it, we told them to pour the concrete slab and allow at least 7 days cure prior to erecting panel.
They are claiming delay and extra cost due to situation. I can't find anywhere where this situation is specifically addressed in our specs. Has anyone else had this problem?
I guess we need a note to tell steel erectors how steel buildings work? Should the precast specification have something about this?
tw
They are claiming delay and extra cost due to situation. I can't find anywhere where this situation is specifically addressed in our specs. Has anyone else had this problem?
I guess we need a note to tell steel erectors how steel buildings work? Should the precast specification have something about this?
tw