Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Preservation for new static equipment like columns, drums and heat exchangers

Status
Not open for further replies.

Ahmed Nasr

Petroleum
Nov 29, 2017
3
Dear All,

Greeting

I want to ask about preservation for new static equipment like columns, drums and heat exchangers. now we are in project and the equipment received at site. Internal installation started form 6 months for columns.

1- Is it required now to purging Nitrogen and/or VPCI bags ?? Because contractor keep all nozzles for column open as they are installing internal parts like trays, weir mesh...

2- Is it applicable for all pressure vessels either stainless steel or carbon steel ??

3- Is there any time limit for working inside and internal installation activities ??

Thanks All,
 
Replies continue below

Recommended for you

How much corrosion can you live with? I assume you will do flushing before putting the equipment in service. Depending on the local environment, you may have to accommodate for additional cleaning/flushing in your commissioning plan.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor