Ahmed Nasr
Petroleum
- Nov 29, 2017
- 3
Dear All,
Greeting
I want to ask about preservation for new static equipment like columns, drums and heat exchangers. now we are in project and the equipment received at site. Internal installation started form 6 months for columns.
1- Is it required now to purging Nitrogen and/or VPCI bags ?? Because contractor keep all nozzles for column open as they are installing internal parts like trays, weir mesh...
2- Is it applicable for all pressure vessels either stainless steel or carbon steel ??
3- Is there any time limit for working inside and internal installation activities ??
Thanks All,
Greeting
I want to ask about preservation for new static equipment like columns, drums and heat exchangers. now we are in project and the equipment received at site. Internal installation started form 6 months for columns.
1- Is it required now to purging Nitrogen and/or VPCI bags ?? Because contractor keep all nozzles for column open as they are installing internal parts like trays, weir mesh...
2- Is it applicable for all pressure vessels either stainless steel or carbon steel ??
3- Is there any time limit for working inside and internal installation activities ??
Thanks All,