garrettk
Geotechnical
- Jan 23, 2004
- 57
I've become involved in a project that has had numerous subsurface investigations over the last 7 years and one piece of the data gathered is Pressure Meter testing.
In the results of the PM testing, there are two modulus values provided, unload/reload modulus and initial modulus. The unload/reload modulus ranges from 3 to 10 times the value of the initial modulus.
The geologic setting consists of a relatively thin soil overburden with severly weathered shale, claystone and thin seams of sandstone underlying. The material is actually called Flysch which is German for flow (I have observed numerous landslides in the area).
The grading plan calls for removing approximately 20 meters of soil/rock from the site prior to construction of foundations which will typically consist of heavily loaded mat foundations - pressures between 400 and 500 kPa.
The question becomes, which modulus should be used when estimating settlement? Most texts reference the use of the initial modulus. However, because we are removing such a large overburden pressure, would it be more appropriate to use the unload/reload modulus provided our foundation loads are less than the overburden pressures?
Obviously this makes a huge difference in the estimated settlements.
Thanks in advance for any advice.
In the results of the PM testing, there are two modulus values provided, unload/reload modulus and initial modulus. The unload/reload modulus ranges from 3 to 10 times the value of the initial modulus.
The geologic setting consists of a relatively thin soil overburden with severly weathered shale, claystone and thin seams of sandstone underlying. The material is actually called Flysch which is German for flow (I have observed numerous landslides in the area).
The grading plan calls for removing approximately 20 meters of soil/rock from the site prior to construction of foundations which will typically consist of heavily loaded mat foundations - pressures between 400 and 500 kPa.
The question becomes, which modulus should be used when estimating settlement? Most texts reference the use of the initial modulus. However, because we are removing such a large overburden pressure, would it be more appropriate to use the unload/reload modulus provided our foundation loads are less than the overburden pressures?
Obviously this makes a huge difference in the estimated settlements.
Thanks in advance for any advice.