posershadow
Chemical
- Nov 30, 2018
- 5
A question came up regarding a pressure vessel we are manufacturing. I included a sketch below for clarity.
We are supplying vessel #1 (blue) which is installed inside a drum (vessel #2). Vessel #1 carries a U-stamp. It has some piping connected to it which is designed to B31.3, the parts in orange are what we are considering as piping. We are also supplying transition joints designed per B31.3 (marked orange with an X), as the metals are dissimilar between our piping (in orange) and the piping (in red) shown. Lastly the SA-106B piping in red is in our scope, but we are going to subcontract the supply of the material to subcontractor #1. The weld in green will be performed by subcontractor #1. So essentially subcontractor #1 is only buying a piece of seamless pipe and performing the weld in green, that is the entirety of their scope.
The vessel #2 will also carry a U-stamp and is being supplied by subcontractor #2, who will take the entire assembly mentioned above and install it inside the drum to finish off the fabrication. They will perform the welds where the piping in red passes through the dished head.
We view the piping (in red) which passes through the dished head as part of vessel #2 and believe it should be designed per Sec. VIII like the rest of the vessel #2. Therefore one of the questions is: does the piping in red need a U-2 partial data form completed by subcontractor #1? If so, then it would likely mean that subcontractor #1 needs a U-stamp. The way we interpret U-1(e)(1)(a) is that the weld in green is beyond the boundary of vessel #2, therefore since subcontractor #1 is only supplying a piece of seamless pipe without any work on the pipe itself inside the vessel boundary, then an MTR is probably the only thing required.
We are hoping a U-2 form isn't required because it will open up additional possible subcontractors who don't carry a U-stamp.
We are supplying vessel #1 (blue) which is installed inside a drum (vessel #2). Vessel #1 carries a U-stamp. It has some piping connected to it which is designed to B31.3, the parts in orange are what we are considering as piping. We are also supplying transition joints designed per B31.3 (marked orange with an X), as the metals are dissimilar between our piping (in orange) and the piping (in red) shown. Lastly the SA-106B piping in red is in our scope, but we are going to subcontract the supply of the material to subcontractor #1. The weld in green will be performed by subcontractor #1. So essentially subcontractor #1 is only buying a piece of seamless pipe and performing the weld in green, that is the entirety of their scope.
The vessel #2 will also carry a U-stamp and is being supplied by subcontractor #2, who will take the entire assembly mentioned above and install it inside the drum to finish off the fabrication. They will perform the welds where the piping in red passes through the dished head.
We view the piping (in red) which passes through the dished head as part of vessel #2 and believe it should be designed per Sec. VIII like the rest of the vessel #2. Therefore one of the questions is: does the piping in red need a U-2 partial data form completed by subcontractor #1? If so, then it would likely mean that subcontractor #1 needs a U-stamp. The way we interpret U-1(e)(1)(a) is that the weld in green is beyond the boundary of vessel #2, therefore since subcontractor #1 is only supplying a piece of seamless pipe without any work on the pipe itself inside the vessel boundary, then an MTR is probably the only thing required.
We are hoping a U-2 form isn't required because it will open up additional possible subcontractors who don't carry a U-stamp.