fastline12
Aerospace
- Jan 27, 2011
- 306
I will have to first mention that this is a private job on my own property but this is a bit outside my area of expertise and looking for standards and data to educate a bit for this as well as get opinions for experienced engineers in the field.
We are building a large pond with a dirt bridge crossing. Crossing will be approx 40-50ft long and 30ft wide. We will basically excavate the entire pond, then install flow pipes to communicate water flow from one side to the other, then back fill to create the crossing area.
I am not sure of what considerations to take regarding load ability of the crossing. I need to decide if PVC pipe is adequate under the crossing or if concrete will be needed.
Soil - sandy loam top, sandy clay under layer.
Max load - 150klb truck load. Not sure if need to break down to psi compression load.
Tube size - 2x, 30-40"
Tube set depth - 6ft
pond depth - 8ft
I realize this is a bit "vague" in data but looking for an overall opinion on the matter I guess.
We are building a large pond with a dirt bridge crossing. Crossing will be approx 40-50ft long and 30ft wide. We will basically excavate the entire pond, then install flow pipes to communicate water flow from one side to the other, then back fill to create the crossing area.
I am not sure of what considerations to take regarding load ability of the crossing. I need to decide if PVC pipe is adequate under the crossing or if concrete will be needed.
Soil - sandy loam top, sandy clay under layer.
Max load - 150klb truck load. Not sure if need to break down to psi compression load.
Tube size - 2x, 30-40"
Tube set depth - 6ft
pond depth - 8ft
I realize this is a bit "vague" in data but looking for an overall opinion on the matter I guess.