jheidt2543
Civil/Environmental
- Sep 23, 2001
- 1,469
Problem, Dilemma and Solution?
The Problem:
I was asked to investigate an existing light manufacturing building built in 1965. There have been two additions to the original building since 1965, one on a sidewall and one at an endwall. The additions resulted in reduced wind load on one sidewall and additional snow loading along an endwall due to drifting from the higher addition. The cause for concern was some distortion of the main frame members and deflection of some of the columns. The structure is a metal building 200’ wide x 125’ long with a 14’ eave height. The original design/build drawings were found, as well as the original structural calculations by the metal building manufacturer (this was a real surprise!). A note on the design/build drawings says in part, "...Omission of knee braces & cross bracing is based on the theory of diaphragm action of a building completely covered inside and outside with 26 ga. metal panels and is to be supported by engineering calculations of the manufacturer". The manufacturer’s structural calculations included diaphragm action calculations as well as restrictions on their use, some of which have been violated.
Upon finding the distortions and deflections after a large snowstorm last winter (2002), the Owner braced some of the framing and removed a large rooftop unit over the affected area. However, the snowstorm was not even close to the nearly record snowfall of 1979 that the building survived.
My investigation confirmed that the X-bracing and knee bracing where left out, which is my immediate concern. The roof and walls both have interior and exterior panels that are in fairly good condition for the diaphragm action. I also suspected, after looking over the original calculations, that the building would not meet current building code requirements; particularly since adoption of the IBC 2000 Code by the local building department. To confirm my suspicions, I sent all the information to the original building manufacturer’s engineering department for review. I asked them to look at the building structure using the original loadings and the new loadings required by the IBC 2000 Code. They agreed that the X-bracing and knee braces should be installed ASAP, as well as reinforcing the roof by adding additional new purlins in the snow drift areas.
The Dilemma:
The Owner is balking at making the recommended changes, which admittedly, will be very expensive. My dilemma is what to do now that I know the building is unsafe in its present condition. As I see it there are three courses of action:
1. Ignore the problem and hope for the best, after all, the building has survived this long without modification. I’ve been paid for my work, now it is up to the Owner. (?)
2. Agree to the partial correction of adding the X-bracing and knee bracing, but not the purlins, which would be the most expensive part of renovation. The bracing is critical for building stability, but the purlins could be a borderline question. The building did survive the major snowstorm of 1979.
3. Contact the local building authorities and let them know of the problem, since it is a life/safety issue. Then wait for the Owner's "blood sucking" attorney's to call me.
Ok fellow engineers, how about some input on this. I think it is a question we all may face at sometime in our career. What say you?
The Problem:
I was asked to investigate an existing light manufacturing building built in 1965. There have been two additions to the original building since 1965, one on a sidewall and one at an endwall. The additions resulted in reduced wind load on one sidewall and additional snow loading along an endwall due to drifting from the higher addition. The cause for concern was some distortion of the main frame members and deflection of some of the columns. The structure is a metal building 200’ wide x 125’ long with a 14’ eave height. The original design/build drawings were found, as well as the original structural calculations by the metal building manufacturer (this was a real surprise!). A note on the design/build drawings says in part, "...Omission of knee braces & cross bracing is based on the theory of diaphragm action of a building completely covered inside and outside with 26 ga. metal panels and is to be supported by engineering calculations of the manufacturer". The manufacturer’s structural calculations included diaphragm action calculations as well as restrictions on their use, some of which have been violated.
Upon finding the distortions and deflections after a large snowstorm last winter (2002), the Owner braced some of the framing and removed a large rooftop unit over the affected area. However, the snowstorm was not even close to the nearly record snowfall of 1979 that the building survived.
My investigation confirmed that the X-bracing and knee bracing where left out, which is my immediate concern. The roof and walls both have interior and exterior panels that are in fairly good condition for the diaphragm action. I also suspected, after looking over the original calculations, that the building would not meet current building code requirements; particularly since adoption of the IBC 2000 Code by the local building department. To confirm my suspicions, I sent all the information to the original building manufacturer’s engineering department for review. I asked them to look at the building structure using the original loadings and the new loadings required by the IBC 2000 Code. They agreed that the X-bracing and knee braces should be installed ASAP, as well as reinforcing the roof by adding additional new purlins in the snow drift areas.
The Dilemma:
The Owner is balking at making the recommended changes, which admittedly, will be very expensive. My dilemma is what to do now that I know the building is unsafe in its present condition. As I see it there are three courses of action:
1. Ignore the problem and hope for the best, after all, the building has survived this long without modification. I’ve been paid for my work, now it is up to the Owner. (?)
2. Agree to the partial correction of adding the X-bracing and knee bracing, but not the purlins, which would be the most expensive part of renovation. The bracing is critical for building stability, but the purlins could be a borderline question. The building did survive the major snowstorm of 1979.
3. Contact the local building authorities and let them know of the problem, since it is a life/safety issue. Then wait for the Owner's "blood sucking" attorney's to call me.
Ok fellow engineers, how about some input on this. I think it is a question we all may face at sometime in our career. What say you?