RPRad
Mechanical
- Nov 12, 2009
- 65
Do you have to do Production Weld impact test if you: A)Have ordered your material already impact tested (yes it is required to meet the MDMT) B)Have qualified Section IX weld procedures which includes impact testing well below the current MDMT and further includes PWHT
Basically I have a thick shell (SA516 Gr. 70N) material(2.5")and a couple of thick nozzles which do not meet the MDMT exemption for a MDMT of -20F (my coincident factor is high due to the design and Corr Allow conditions). Obviously I am not exempted under UG-20(f), the material was ordered impact tested and came from the material manufacturer impact tested to -50F. My current weld procedures cover both weld zone impact testing down to -50F and PWHT which I am required to do in this case because of thickness
It almost appears that I need to use UCS-67(a)to exempt myself out of UG-84(h) and subsequently UG-84(i) in order to not do the production tests
Perhaps I am interpreting wrong but I dont see the point of doing production tests if my material and weld procedures are both impact tested well below the MDMT...this could not be the intent of the Code...there are situations (ie heavy weld passes) where I could see doing this but this doesnt strike me as one of them
Anybody know the intent of the Code in this case, in talking to other manufacturers they rarely do production test as well...but admittedly most agree interpretation appears confusing...is there an ASME interpretation that covers this situation?
Basically I have a thick shell (SA516 Gr. 70N) material(2.5")and a couple of thick nozzles which do not meet the MDMT exemption for a MDMT of -20F (my coincident factor is high due to the design and Corr Allow conditions). Obviously I am not exempted under UG-20(f), the material was ordered impact tested and came from the material manufacturer impact tested to -50F. My current weld procedures cover both weld zone impact testing down to -50F and PWHT which I am required to do in this case because of thickness
It almost appears that I need to use UCS-67(a)to exempt myself out of UG-84(h) and subsequently UG-84(i) in order to not do the production tests
Perhaps I am interpreting wrong but I dont see the point of doing production tests if my material and weld procedures are both impact tested well below the MDMT...this could not be the intent of the Code...there are situations (ie heavy weld passes) where I could see doing this but this doesnt strike me as one of them
Anybody know the intent of the Code in this case, in talking to other manufacturers they rarely do production test as well...but admittedly most agree interpretation appears confusing...is there an ASME interpretation that covers this situation?