luca1983
Computer
- Mar 13, 2005
- 1
hey there i really need some help with a quite large project i'm working on.. i have got all the task done and the durations which are mostly one hour or 2 hours. there is about 170 tasks and the total duration is comming up at only 2.5 days.. i have linked all the Predecessors properly and the working time for the project is only one day a week for four hours.. so i have no idea why it is saying the project will last 2.5 days... any help on this would really be appreciated
thanks
thanks