MarshfieldTimC
Civil/Environmental
- Dec 10, 2002
- 33
I have a project that requires connecting a collector sanitary sewer (12") to an interceptor sewer. The existing interceptor is 60" reinforced concrete and approximately 25' deep. I would like build the proposed manhole as an outside drop manhole. I am considering a poured-in-place, reinforced bottom section that does not disturb the integrity of the existing 60" pipe, except that the top of the pipe will be removed. (The manhole would be formed around the existing 60" pipe.) The remaining risers would be 48" precast concrete. Anybody have any experience with a project/manhole such as this?
(Thanks in advance for all responses.)
(Thanks in advance for all responses.)