peteryoull123
Civil/Environmental
- Jul 19, 2012
- 3
Hi all,
Im currently attempting to write a program to identify which type of sanitation system would be most cost effective in slums, based on a few simple input parameters about the site. As such, I am having to make some assumptions and estimates. I was hoping to get peoples proffesional opinion on a few things.
The first question I have:
I am designing a pipe sewerage network as one of the options under anaylsis. I have to make an assumption based upon how long it will take one worker to prop a trench. Whilst I am aware that it would not really be just one worker, and it will be entirely dependant upon the ground type I just need a ball park figure. The outcome of the program aims to be accurate to within 30% of the acutal costs and is only aimed at offering a suggestion as to which solutions will be most cost effective for further analysis. My initial thoughts would be that one man could prop around 2 sq.m of trench per hour, however I have no practical experience to base this on. (or a team of 2 men could manage 4 sq.m per hour). This calculation is simply to estimate the labour cost of propping a trench, and so in reality it could be a team of workers propping working over a much shorter time scale.
The second question I have, and I am aware this should be in a different area:
When excavating in undulating or hilly land, will the life cycle costs of installing very deep sewer lines (~6m) to allow the pipeline to cross trough to trough over a hillock be higher or lower than installing much shallower pipes with a pumping station to get the sewerage over the hill. It would seem logical to me that the deep lines would be more cost effective over 25 years, as you will not have to have electricity and maintenance on pumps etc, however I was wondering whether anyone has experience of this and could offer a suggestion.
Thanks in advance!, Peter
Im currently attempting to write a program to identify which type of sanitation system would be most cost effective in slums, based on a few simple input parameters about the site. As such, I am having to make some assumptions and estimates. I was hoping to get peoples proffesional opinion on a few things.
The first question I have:
I am designing a pipe sewerage network as one of the options under anaylsis. I have to make an assumption based upon how long it will take one worker to prop a trench. Whilst I am aware that it would not really be just one worker, and it will be entirely dependant upon the ground type I just need a ball park figure. The outcome of the program aims to be accurate to within 30% of the acutal costs and is only aimed at offering a suggestion as to which solutions will be most cost effective for further analysis. My initial thoughts would be that one man could prop around 2 sq.m of trench per hour, however I have no practical experience to base this on. (or a team of 2 men could manage 4 sq.m per hour). This calculation is simply to estimate the labour cost of propping a trench, and so in reality it could be a team of workers propping working over a much shorter time scale.
The second question I have, and I am aware this should be in a different area:
When excavating in undulating or hilly land, will the life cycle costs of installing very deep sewer lines (~6m) to allow the pipeline to cross trough to trough over a hillock be higher or lower than installing much shallower pipes with a pumping station to get the sewerage over the hill. It would seem logical to me that the deep lines would be more cost effective over 25 years, as you will not have to have electricity and maintenance on pumps etc, however I was wondering whether anyone has experience of this and could offer a suggestion.
Thanks in advance!, Peter