DeathRay009
Mechanical
- Jan 7, 2024
- 15
Hi all,
We are currently in the process of ordering a div. II heat exchanger from a vendor. As per table 7.2 of ASME Div. II, some welds require PT/MT inspection. The code however fails to mention if the PT/MT is to be done on either root pass or final pass or both. This is where we are disagreeing with our vendor since he want to do PT on root pass only.
Your expertise in this regard is requested.
We are currently in the process of ordering a div. II heat exchanger from a vendor. As per table 7.2 of ASME Div. II, some welds require PT/MT inspection. The code however fails to mention if the PT/MT is to be done on either root pass or final pass or both. This is where we are disagreeing with our vendor since he want to do PT on root pass only.
Your expertise in this regard is requested.