Andy J
Civil/Environmental
- Dec 3, 2016
- 24
Looked at a PT Slab and there is a no 4 rebar tied around the edge of the slab behind the cable anchors. They told me they do that to keep the anchors from popping out of the slab but it seems like it would limit the cable pull to just where the anchors are, but maybe there isn't enough bond between the cables and the rebar to keep the cable from being pulled.