BenjaminM
Chemical
- Dec 12, 2006
- 86
Good evening all,
I have a Goulds 6x8-15/11.5 731+ pump running at 1750 rpm. Looking at the curve the pump is rated for 2000 gpm at 100 ft head. The curve shows our 75 hp motor should be more than sufficient.
We are planning on switching a condenser over to the cooling tower loop this pump supplies. The condenser only requires 250 gpm, and is approximately 50 ft in elevation.
With out doing extensive friction loss calculations on the run of 4 & 8 inch pipe between the pump and the condenser, I wanted to do just a simple double check to see how much power was required to move a quantity of 250 gal of water, 50 ft in the air every minute. What I came up with doesn't make sense, what did I do wrong?
250 gal = 2090 lbm (pound mass)
Height = 50 ft
Weight x gravity x height = change in potential energy
(2900 lbm) x (32 ft/s2) x (50 ft) = 3,344,000 lbm*ft2/s2
1 lbs*ft/s2 = 1 lbf (pound force)
3,344,000 lbf*ft, this is actually per minute, so divide by 60.
55,700 lbf*ft/s
And 550 lbf*ft/s = 1 hp
So 100 hp is required to move 250 gallons up 50 ft. This can't be the case as 75 hp is capable of doing nearly x20 as much!
What did I miss? Was my assumption that the increase in potential energy would be equal to the work done wrong?
I have a Goulds 6x8-15/11.5 731+ pump running at 1750 rpm. Looking at the curve the pump is rated for 2000 gpm at 100 ft head. The curve shows our 75 hp motor should be more than sufficient.
We are planning on switching a condenser over to the cooling tower loop this pump supplies. The condenser only requires 250 gpm, and is approximately 50 ft in elevation.
With out doing extensive friction loss calculations on the run of 4 & 8 inch pipe between the pump and the condenser, I wanted to do just a simple double check to see how much power was required to move a quantity of 250 gal of water, 50 ft in the air every minute. What I came up with doesn't make sense, what did I do wrong?
250 gal = 2090 lbm (pound mass)
Height = 50 ft
Weight x gravity x height = change in potential energy
(2900 lbm) x (32 ft/s2) x (50 ft) = 3,344,000 lbm*ft2/s2
1 lbs*ft/s2 = 1 lbf (pound force)
3,344,000 lbf*ft, this is actually per minute, so divide by 60.
55,700 lbf*ft/s
And 550 lbf*ft/s = 1 hp
So 100 hp is required to move 250 gallons up 50 ft. This can't be the case as 75 hp is capable of doing nearly x20 as much!
What did I miss? Was my assumption that the increase in potential energy would be equal to the work done wrong?