Hi,
I am designing an embankment with preloading and PVD installation, we did define the critera at the end of preloading and we have a generous preloading period of 3 years it comes up that drains spacing to be 3 to 3.5 m depending on fill height.
Any one have an experience with PVD in such spacing ?
I know this spacing would work for sand drains very well and I worked with PVD in 1-1.8m spacing but not in the range of 3 m...any comments
thanks
CD
I am designing an embankment with preloading and PVD installation, we did define the critera at the end of preloading and we have a generous preloading period of 3 years it comes up that drains spacing to be 3 to 3.5 m depending on fill height.
Any one have an experience with PVD in such spacing ?
I know this spacing would work for sand drains very well and I worked with PVD in 1-1.8m spacing but not in the range of 3 m...any comments