hollerg
Chemical
- Mar 22, 1999
- 97
I have read that pool fires consume 3-4 mm of fuel per minute. I am reviewing the relief requirements in a moderately sized batch plant. The area has a drain that is maintained open, but some material will pool until the spilled volume drains away. The liquids in the area are 1B flammables
A) Is it proper to limit the fire scenario to the time to burn off/drain the maximum spill inventory within that containment area, in smaller plants?
Assume that there are remote (hand operated) valves that exist for sources to the area, but that the access to those valves is clear because they are larger but remote, raw material storage tanks.
B) If I compute that the vessel cannot be heated to the disk burst point by that fire scenario, is this no longer a credible case?
C) Is there any design approach for jet fire impingement, or would I need this only when handling Class 1A flammables or pressurized gaseous processes?
D) For a reduced duration fire, does anyone have data on how long a stainless steel over-jacket on 2" of fiberglass insulation can be counted on to last before it has no insulation value?
E) Do any companies say that making allowances for the duration, as described above is considered good engineering practice?
A) Is it proper to limit the fire scenario to the time to burn off/drain the maximum spill inventory within that containment area, in smaller plants?
Assume that there are remote (hand operated) valves that exist for sources to the area, but that the access to those valves is clear because they are larger but remote, raw material storage tanks.
B) If I compute that the vessel cannot be heated to the disk burst point by that fire scenario, is this no longer a credible case?
C) Is there any design approach for jet fire impingement, or would I need this only when handling Class 1A flammables or pressurized gaseous processes?
D) For a reduced duration fire, does anyone have data on how long a stainless steel over-jacket on 2" of fiberglass insulation can be counted on to last before it has no insulation value?
E) Do any companies say that making allowances for the duration, as described above is considered good engineering practice?