saipemsmspetti
Industrial
- Dec 21, 2005
- 24
Is it possible per ASME IX and B 31.3 and B 31.8 to have qualified WPS with PWHT and to avoid qualification for the repair with same essential variables using qualified previous main WPS procedure. The second PWHT will be performed after repair in the same way as qualified by the main WPS.