Im designing a sprinler system for a hvac metal workshop, it will have some lockformer machines, a duct fabric line and a vulcan cut table. Ive read in nfpa 13 that a metal workshop should be classified as a occupancie Ordinary hazard 2, but i have the concern that the ceiling its pretty high, like 23 feet.
For the occupancies i dont see any regulations for the maximun height of the srpinkler system?? can anyone give me some adivice on this??? Thanks.
For the occupancies i dont see any regulations for the maximun height of the srpinkler system?? can anyone give me some adivice on this??? Thanks.