I am mulling over the situation where an FPE designs a project that is bid out and built without the same FPE involved in construction support. The dilemna is the designer of record is no longer involved, it is in the contractors hands. However, a FPE is needed to sign off on the prelim and final acceptance tests.
Q1: What approaches have you seen for this situation?
Q2: Would you as an FPE be comfortable simply signing your signature (but not placing PE seal) to the final acceptance test report, and providing written certification that the sprinkler system is installed in accordance with the contract requirements?
Q3: Would you be comfortable placing a submittal review stamp on the shop drawings if the sprinkler sub were to sub the engineering to you?
Thanks!