John2004
Mechanical
- Mar 29, 2004
- 237
Hello,
I hired a contractor to build a room addition. The single storey room has a concrete basement with standard wood frame construction built on the basements walls. The room is about 26 feet long X 19 feet wide. The 2 X 10 SYP wood floor joists run lengthwise along the 26' span & hang over one of the basement walls (along the 26' span) by about 4 feet. The joists are 18" O.C. & are supported by an 8 X 5-1/2" steel "I" beam, located at the center of the 22 foot span of the basement walls (26 - 4 = 22).
The joists "overlap" each other at the steel beam (by a couple feet) and do not run the full 26' length.
The basement walls are 8" thick, and the steel "I" beam fits down into "notches" in the center of the two 22'long walls.
The steel "I" beam is supported by a round hollow steel support tube at the center of the approximate 19' span of the steel "I" beam. The support tube is about 4-1/2" in diameter & has a threaded height adjustment on the bottom. The bottom of the tube is connected to a steel "pad" that is bolted to the concrete floor. The top of the tube connects with a bracket that is "wrapped around" the bottom of the "I" beam.
However, the ends of the steel "I" beam are not sitting down on the concrete walls, and are not touching the basement walls in any way. The "I" beam is being completely supported by the steel support tube in the center of the 19' span of the "I" beam.
They cut a few steel shims and put them under each end of the steel "I" beam, between the beam and the concrete walls (shims are about 1/8" to 3/16" thick X 2-1/2" wide X 6" long. They have two shims on one side, and one shim on the other.
However, there is still a 1/8" to 1/4" gap on each end, between the bottom of the steel "I" beam and the shims. So, the steel "I" beam is being completely supported by the support tube, and not the basement walls.
Is this the correct way to install the "I" beam ? The contractor said it was, and that there would be some settling.
It just seems to me that the steel beam should be supported by the basement walls on each end (i.e., it should be sitting on the basement walls) and then the steel support tube should just "support" the center of the steel beam, and not be the "only" thing that holds the entire beam (and the center of the floor) in mid air.
I suppose if the center support beam would change in length due to ambient air temperature, then this might be one reason to leave a gap at each end of the "I" beam. If the center support beam were to shorten due to temperature changes, then it could pull the bolts out of the concrete floor (or at least loosen them) since the support tube is fastened to the "I" beam. I suppose the "I" beam could change a little in size as well, but I would not think it would be much.
It seems to me any settling would just make the gaps bigger at each end of the steel beam.
I would appreciate it if someone could please educate me a little in this area and explain the proper way to install a steel support beam in a situation like this, and explain why it is done that way.
Thanks for your help.
John
I hired a contractor to build a room addition. The single storey room has a concrete basement with standard wood frame construction built on the basements walls. The room is about 26 feet long X 19 feet wide. The 2 X 10 SYP wood floor joists run lengthwise along the 26' span & hang over one of the basement walls (along the 26' span) by about 4 feet. The joists are 18" O.C. & are supported by an 8 X 5-1/2" steel "I" beam, located at the center of the 22 foot span of the basement walls (26 - 4 = 22).
The joists "overlap" each other at the steel beam (by a couple feet) and do not run the full 26' length.
The basement walls are 8" thick, and the steel "I" beam fits down into "notches" in the center of the two 22'long walls.
The steel "I" beam is supported by a round hollow steel support tube at the center of the approximate 19' span of the steel "I" beam. The support tube is about 4-1/2" in diameter & has a threaded height adjustment on the bottom. The bottom of the tube is connected to a steel "pad" that is bolted to the concrete floor. The top of the tube connects with a bracket that is "wrapped around" the bottom of the "I" beam.
However, the ends of the steel "I" beam are not sitting down on the concrete walls, and are not touching the basement walls in any way. The "I" beam is being completely supported by the steel support tube in the center of the 19' span of the "I" beam.
They cut a few steel shims and put them under each end of the steel "I" beam, between the beam and the concrete walls (shims are about 1/8" to 3/16" thick X 2-1/2" wide X 6" long. They have two shims on one side, and one shim on the other.
However, there is still a 1/8" to 1/4" gap on each end, between the bottom of the steel "I" beam and the shims. So, the steel "I" beam is being completely supported by the support tube, and not the basement walls.
Is this the correct way to install the "I" beam ? The contractor said it was, and that there would be some settling.
It just seems to me that the steel beam should be supported by the basement walls on each end (i.e., it should be sitting on the basement walls) and then the steel support tube should just "support" the center of the steel beam, and not be the "only" thing that holds the entire beam (and the center of the floor) in mid air.
I suppose if the center support beam would change in length due to ambient air temperature, then this might be one reason to leave a gap at each end of the "I" beam. If the center support beam were to shorten due to temperature changes, then it could pull the bolts out of the concrete floor (or at least loosen them) since the support tube is fastened to the "I" beam. I suppose the "I" beam could change a little in size as well, but I would not think it would be much.
It seems to me any settling would just make the gaps bigger at each end of the steel beam.
I would appreciate it if someone could please educate me a little in this area and explain the proper way to install a steel support beam in a situation like this, and explain why it is done that way.
Thanks for your help.
John