NoWittyHandle
Geotechnical
- Mar 24, 2003
- 36
Our firm is representing a homeowner's association for a development that was built on a deposit of miscellaneous fill and organic silt. The fill was as much as thirty feet thick, and the organic silt was as much as forty feet thick. The project consists of two-story attached units supported on shallow spread footings. Dynamic compaction was used to consolidate the fill, and drainage wicks were installed in the organic silt during surcharging.
I am in the process of going through the documents related to the site, and I have identified some problems with how the work was constructed, but I have several questions relating to surcharging. Given these soil conditions, how well could the best surcharge program be expected to perform? How much additional settlement can be expected if the surcharge is removed before the organic silt has had a chance to consolidate under the surchage load, even if all of the expected primary and one cycle of secondary settlement has occured? Thank you for your responses.
I am in the process of going through the documents related to the site, and I have identified some problems with how the work was constructed, but I have several questions relating to surcharging. Given these soil conditions, how well could the best surcharge program be expected to perform? How much additional settlement can be expected if the surcharge is removed before the organic silt has had a chance to consolidate under the surchage load, even if all of the expected primary and one cycle of secondary settlement has occured? Thank you for your responses.