Jake52
Mechanical
- Jul 2, 2003
- 1
Question on "Self-Springing" of High Energy Piping (HEP).
Ref: B31.1 Power Piping Code, Sec. 119.2 "Stress Range".
Given the following scenario:
-HEP Steam System on new combined cycle power plant.
-Chrome-Moly Piping Material (P91 & P22).
-Max Operating Temperature of 1065 degrees F
-Design Pressure 400 PSIG
-Runs at max temp for 6 wks, (1008 hrs) before 1st shutdown.
-System initially fabricated correctly.
[Zero gap @ Final Field Weld, (FFW) during installation].
-All System stresses well within Code allowables.
Q1. How soon does the self-springing process begin?
Q2. If pipe is cooled/cut @ FFW after 1080 hrs of operation:
Would a gap be present at the FFW after the cut?
Q3. Suggested references for further investigation?
Ref: B31.1 Power Piping Code, Sec. 119.2 "Stress Range".
Given the following scenario:
-HEP Steam System on new combined cycle power plant.
-Chrome-Moly Piping Material (P91 & P22).
-Max Operating Temperature of 1065 degrees F
-Design Pressure 400 PSIG
-Runs at max temp for 6 wks, (1008 hrs) before 1st shutdown.
-System initially fabricated correctly.
[Zero gap @ Final Field Weld, (FFW) during installation].
-All System stresses well within Code allowables.
Q1. How soon does the self-springing process begin?
Q2. If pipe is cooled/cut @ FFW after 1080 hrs of operation:
Would a gap be present at the FFW after the cut?
Q3. Suggested references for further investigation?